Highlights: Feasibility Studies Progress
Processing plant design incorporating the 2,300tpd SAG Mill purchased by Condor, has been 100% completed. Associated infrastructure designs and costs are under development.
A surface water hydrological model has been 100% completed, which feeds into the Site Wide Water Balance, with the supporting documentation due by the end of October. Detailed water management structure designs are underway.
Tailings Storage Facility ("TSF") design has been 100% completed, the draft report was delivered to Condor during the first week in October. The report is under review by Condor, with the material take-offs for construction passed to Hanlon Engineering for cost estimation.
The stormwater attenuation structure at La Simona is under design and is 90% completed. As with the TSF, the material take-offs will be passed to Hanlon to estimate the construction costs.
Metallurgical Studies - Analytical work is 95+% completed. A draft report is due by the end of October.
Mineral Resource Estimate update. All assays from the infill drilling program have been received. Updates to the geological framework inclusive of the lithological, structural and weathering model are approximately 80% complete. Once completed the Mineral Resource estimate update for La India will commence.
Pit Geotechnical - a review of the initial round of 1700 m of geotechnical drilling by SRK indicated that an additional 690m of oriented core drilling, followed by televiewer logging, will be required to meet FS level confidence. Completion of the drilling and logging is expected by mid November, with televiewer inspection to be conducted upon completion of each hole.
Hydrogeology / pit water management - Condor successfully intercepted the deepest level of the 1950s-era underground mine workings in hole LIDC 178, providing confidence that said workings are suitable to tap in to, in order to draw down ground water levels and support depressurization of the pit slopes. A test borehole close to the historical mineshaft will be drilled in November to one of the options for the location of the long-term pumping station.