The selection and piloting of the beneficiation flowsheet and the completion of the pilot plant that became operational in November 2015 are integral to the bankable feasibility study (BFS), as they validate the projects viability.
We have [established] a pilot plant for our beneficiation process and this will be followed by a pilot leach plant, which is scheduled to start in the first quarter of [2016]. These pilot plants, combined with the earlier results from Peaks 2013 solvent extraction pilot plant, will provide all the design parameters for the process plant work to be completed for the BFS.
Peak intends to complete the BFS by the end of this year and will decide on the construction schedule prior to the end of 2017. Plant commissioning and first production are expected in 2018/19. The company expects to employ about 150 people once processing operations start officially.