10.02.24 11:07
Ascot Provides Update On Previously Announced Financing Package

February 9, 2024

ancouver, B.C. February 9, 2024— Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF) (“Ascot” or the “Company”) is pleased to announce that the Company has finalized the terms of definitive documentation for a total of approximately US$50 million in funding from Sprott Resource Streaming and Royalty Corp. and/or its affiliates (“Sprott Streaming”) and Nebari Natural Resources Credit Fund II, LP (“Nebari”), as further described in the Company’s news release dated January 22, 2024. Ascot, Sprott Streaming and Nebari have signed the definitive documentation into escrow with an anticipated effective date of February 20, 2024.

The Company is also announcing that the closing date for the previously announced bought deal financing with a syndicate of underwriters co-led by BMO Capital Markets and Desjardins Capital Markets, as further described in the Company’s news release dated January 22, 2024, is now scheduled to occur on February 20, 2024.

The Company has received TSX conditional approval for the transactions described herein, however, the closing of the bought deal financing remains subject to customary closing conditions. The release from escrow of the definitive documentation executed by Ascot, Sprott Streaming and Nebari is subject to the parties’ express release upon the concurrent completion of the bought deal financing and the submission for registration of certain debentures in the Land Title Office of British Columbia and in the Mineral Titles Online of British Columbia.

Any securities offered have not been registered under the U.S. Securities Act of 1933, as amended, and may not be offered or sold in the United States absent registration or an applicable exemption from the registration requirements. This press release shall not constitute an offer to sell or the solicitation of an offer to buy nor shall there be any sale of the securities in any State in which such offer, solicitation or sale would be unlawful.

ascotgold.com/news-releases/2024/...ounced-financing-package/

Werbung

Entdecke die beliebtesten ETFs von Xtrackers

Xtrackers S&P 500 2x Leveraged Daily Swap UCITS ETF 1C
Perf. 12M: +63,42%
Xtrackers LevDAX Daily Swap UCITS ETF 1C
Perf. 12M: +52,38%
Xtrackers MSCI USA Banks UCITS ETF 1D
Perf. 12M: +47,73%
Xtrackers MSCI Pakistan Swap UCITS ETF 1C
Perf. 12M: +45,89%
Xtrackers MSCI USA Information Technology UCITS ETF 1D
Perf. 12M: +42,52%

peter47:

Ascot Closes Financing for Completion and Ramp-Up

 
24.02.24 09:23
Ascot Closes Financing for Completion and Ramp-Up of the Premier Gold Project

ASCOT CLOSES C$29 MILLION BOUGHT DEAL FINANCING AND US$50 MILLION IN ADDITIONAL FUNDING FOR COMPLETION AND RAMP-UP OF THE PREMIER GOLD PROJECT

Vancouver, B.C. February 20, 2024 — Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF) (“Ascot” or the “Company”) is pleased to announce that the Company has closed its financing for a total of US$50 million from Sprott Resource Streaming and Royalty Corp. and/or its affiliates (“Sprott Streaming”) and Nebari Natural Resources Credit Fund II, LP (“Nebari”), as further described in the Company’s news release dated January 22, 2024.

Concurrently, the Company closed its previously announced bought deal private placement financing with a syndicate of underwriters co-led by BMO Capital Markets and Desjardins Capital Markets (together, the “Joint Bookrunners”), and including CIBC World Markets Inc., Raymond James Ltd. and Velocity Trade Capital Ltd. (collectively, with the Joint Bookrunners, the “Underwriters”). Under the bought deal financing, the Company issued a total of 65,343,000 common shares of the Company (the “Common Shares”) at a price of C$0.44 per Common Share, for gross proceeds of approximately C$29 million, which included the full exercise of the Underwriters’ option.

Derek White, President and CEO, commented: "We commend our financing partners Sprott Streaming and Nebari for their cooperation and timely closing for this financing. We express our gratitude to our existing shareholders who participated in the bought deal financing, including our largest shareholder Ccori Apu S.A.C., and welcome new institutional shareholders whose support is very much appreciated.”

Michael Harrison, Managing Partner at Sprott Streaming, commented: “We are very pleased to expand our partnership and continue to support Ascot Resources as the team prepares for imminent production from the Premier Gold Project. Sprott Streaming continues to provide funding to advance quality projects and provide project financing to bring mines into production.”

Nebari Managing Director, Juan Alvarez, stated: “We are very pleased to be providing additional funding to Ascot in the form of a cost overrun facility as support for the construction and ramp-up of the Premier Gold Project.”

ascotgold.com/news-releases/2024/...the-premier-gold-project/
peter47:

Ascot Provides Construction Update on the Premier

 
24.02.24 09:26
Ascot Provides Construction Update on the Premier Gold Project

Vancouver, B.C. February 20, 2024 — Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF)  (“Ascot” or the “Company”) is pleased to provide a construction update on the Company’s Premier Gold Project (“PGP” or the “Project”), located on Nisga’a Nation Treaty Lands in the prolific Golden Triangle of northwestern British Columbia. Project construction was 86% complete as of December 31, 2023 (approximately 90% as of January 31, 2024) and is currently nearing completion, with first ore delivery to the mill anticipated by the end of March 2024, and first gold pour anticipated in April.

Derek White, President and CEO, commented, "With Project construction nearing completion and early commissioning underway, we eagerly anticipate progressing to the production and operations phase at the Premier Gold Mine. The Project also accomplished an impressive safety milestone having surpassed one million hours without a lost time incident, along with another quarterly reduction in total recordable incident frequency. We are also proud to have recently closed an additional financing package which we believe is sufficient for the Company to progress from construction to first gold pour, ramp-up, commercial production and steady-state operations. With the gold price still trading near US$2,000 per ounce, this is an opportune time for us to become Canada’s next gold producer.”

ascotgold.com/news-releases/2024/...the-premier-gold-project/
peter47:

Ascot Reports 2023 Annual Results

 
29.03.24 11:59
March 26, 2024

ASCOT REPORTS 2023 ANNUAL RESULTS

Vancouver, B.C. March 26, 2024 — Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF)  (“Ascot” or the “Company”) announces the Company's audited consolidated financial results for the year ended December 31, 2023. For details of the audited consolidated financial statements, Management's Discussion and Analysis, and Annual Information Form for the year ended December 31, 2023, please see the Company's filings on SEDAR+ at www.sedarplus.ca.

All amounts herein are reported in $000s of Canadian dollars (“C$”) unless otherwise specified.

2023 AND RECENT HIGHLIGHTS

On February 20, 2024, the Company closed its previously announced financing package for a total of US$50 million from Sprott Resource Streaming and Royalty Corp. and its affiliates (“Sprott Streaming”) and Nebari Credit Fund II, LP (“Nebari Credit Fund II”), as described in the Company’s news release dated January 22, 2024. $13,700 of the above proceeds was used to buy back two existing 5% NSR royalties on various Premier Gold Project (“PGP”) property claims, which was completed on March 15, 2024.
On February 20, 2024, concurrently with the above-noted financing package, the Company closed its previously announced bought deal private placement financing, under which the Company issued a total of 65,343,000 common shares of the Company (the “Common Shares”) at a price of C$0.44 per Common Share, for gross proceeds of $28,751.
At the end of Q4 2023, overall construction excluding mine development was 86% complete (approximately 94% as of February 29, 2024), compared with 66% complete at the end of Q3 2023. Numerous pre-commissioning activities in the mill have commenced. The Company anticipates introducing first ore into the mill by the end of March 2024, and pouring first gold in April.
PGP reached an important safety milestone in Q4 of 2023: one million hours without lost time incidents (“LTI”). By the end of Q4 2023, this figure reached 1,143,029 hours LTI free. The total recordable incident frequency has been reduced yet again from 0.69 at the end of Q3 2023 to 0.52 by the end of Q4 2023.
At the tailings storage facility (“TSF”), the south dam, north dam, and southeast dam have been completed. The minor remaining work is focused on the smaller east dam and spillway which is expected to be completed by the end of March. The new electrical substation was completed and all 138kV power lines were pulled and linked up with the BC Hydro grid. Site powerup on the 138 kV line was completed in January 2024.
The new water treatment plant was fully commissioned and began operations in February 2024. The high-density sludge plant has been successfully commissioned and water is being treated and discharged into the environment. The moving bed bio-reactor is mechanically and electrically complete and media is being loaded into the tanks. The plant is anticipated to be brought into service by the end of March 2024.
In October 2023, the Company obtained a temporary use permit to install a camp facility in the town of Stewart to provide additional accommodations for workers at the Project. The Company mobilized and installed living quarters with an initial capacity of 76 beds in early December 2023. This has alleviated some of the pressure caused by the extended earthworks schedule.
On September 19, 2023, the Company acquired a full-service laboratory facility (“Assay Lab”) in Stewart, BC from Seacan Labs Corp. The Assay Lab will be used to perform the testing required by Ascot for mineral exploration, mining operation, and environmental monitoring. During Q4 2023, the Assay Lab was re-commissioned for use and is currently ramping up toward full capacity of 250-300 samples per day with a 24-hour turnaround.
In Q3 2023, the Company’s underground mining contractor Procon Mining & Tunnelling mobilized to site. In Q4 2023, underground development at Big Missouri was re-commenced and is ongoing. As of March 21, 2024, underground development at Big Missouri totaled approximately 2,091 metres. In late 2023, underground decline development commenced on the new Premier Portal close to the mill. Mining development is being advanced down into the Premier deposit for initial mining in the Prew Zone, with ore development anticipated to begin in Q2 2024, and stope production following in Q3 2024. As of March 15, 2024, underground development at Premier totaled approximately 32 metres.
On June 27, 2023, the Company closed a previously announced US$14 million subordinated convertible credit facility (the “Convertible Facility”) with Nebari Gold Fund 1, LP (“Nebari”). The full proceeds from the Convertible Facility were used to repay principal, accrued interest and fees of Ascot’s existing subordinated convertible credit facility with Beedie Investments Ltd. (“Beedie”).
On April 20, 2023, the Company closed a previously announced non-brokered private placement for total gross proceeds of $4,050 and consisted of 5,000,000 common shares of the Company, which qualify as "flow-through shares" within the meaning of the Income Tax Act (Canada) (the “FT Shares”), at a price of C$0.81 per FT Share.
   The Company’s 2023 exploration program at PGP commenced in May, which consisted of 88 holes totaling 11,886 metres and included exploration drilling for resource expansion as well as in-fill drilling of initial mining areas at the Big Missouri and Premier deposits. Assay results were announced between August 2023 and January 2024. Multiple high-grade intercepts were drilled, including 98.84 g/t Au over 6.48m from a depth of 51.5m in hole P23-2490, including 691.50 g/t Au over 0.90m. This was the all-time second highest-grade drill intercept at Big Missouri and is the Company’s highest-grade drill intercept property-wide since 2015.
   On January 19, 2023, the Company closed a previously announced financing package. The financing package consisted of US$110 million as a deposit in respect of gold and silver streaming agreements and a strategic equity investment of C$45 million, a portion of which is structured as Canadian Development Expenditures flow through shares, such that the total gross proceeds to the Company was C$50 million.

FINANCIAL RESULTS FOR THE THREE MONTHS AND YEAR ENDED DECEMBER 31, 2023

The Company reported a net income of $1,705 for Q4 2023 compared to a net loss of $5,988 for Q4 2022. The net income in Q4 2023 is mainly driven by the accounting gain on increase in fair value of the stream buyback embedded derivatives as a result of increase in gold prices and a decrease in market credit spreads.

The Company reported a net loss of $10,430 for 2023 compared to $10,808 for 2022. The lower net loss is attributable to a combination of key factors including a $2,405 decrease in stock-based compensation, and a $1,539 increase in gain on change in fair value of the Stream buyback embedded derivatives, partially offset by a $1,392 increase in environmental compliance costs, and a $1,202 increase in deferred income tax expense.

LIQUIDITY AND CAPITAL RESOURCES

As at December 31, 2023, the Company had cash & cash equivalents of $26,974 and working capital deficiency of $18,337. On February 20, 2024, the Company closed a bought deal private placement for gross proceeds of $28,751 and a US$50 million financing package consisting of a royalty restructuring and a cost overrun facility. Management considered the negative net working capital and the commitments that had existed at December 31, 2023 as well as the funding received subsequent to year end and concluded that the Company now has sufficient funding for the next twelve months of operations, including to progress from construction to first gold pour, ramp-up, commercial production and eventually steady-state operations.

During 2023, the Company issued 120,186,206 common shares, granted 9,789,358 stock options, issued 1,449,973 Deferred Share Units and 2,606,908 Restricted Share Units. Also, 564,152 stock options expired or were forfeited, and 55,530 stock options, 452,006 Deferred Share Units and 721,597 Restricted Share Units were exercised in 2023.

MANAGEMENT’S OUTLOOK FOR 2024

With the financing package closed on February 20, 2024, the Company believes that it has sufficient funding to complete construction and ramp-up of PGP in 2024. The key activities for remainder of 2024 include:

   Advancing the mining development at Big Missouri and at Premier, with stoping activity at Premier starting in Q3 2024
   Completing recruitment of operating team personnel by the end of March 2024
   First ore to the mill by the end of March 2024 and first gold pour in April 2024, and commercial production in Q3 2024

Qualified Person

John Kiernan, P.Eng., Chief Operating Officer of the Company is the Company’s Qualified Person (QP) as defined by National Instrument 43-101 and has reviewed and approved the technical contents of this news release.

On behalf of the Board of Directors of Ascot Resources Ltd.

“Derek C. White”

President & CEO

ascotgold.com/news-releases/2024/...orts-2023-annual-results/
peter47:

Ascot Commences Ore Processing at the Premier Gold

 
13.04.24 21:08
Ascot Commences Ore Processing at the Premier Gold Project

Vancouver, B.C. April 8, 2024 — Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF)  (“Ascot” or the “Company”) is pleased to announce the commencement of ore processing at the Premier Gold Project (“PGP” or the “Project”), located on Nisga’a Nation Treaty Lands in the prolific Golden Triangle of northwestern British Columbia. Rock was introduced into the grinding circuit of the mill on March 31, 2024, and the first ore was introduced into the mill on April 5, 2024.

Derek White, President and CEO, commented, "The start of ore processing is a momentous achievement for the whole team at Ascot and an exciting milestone for the Company. Most project construction activities are substantially completed, and commissioning activities are ongoing throughout the processing plant with the aim of pouring first gold this month.”

As is customary for processing plant start-ups, waste rock was initially introduced into the grinding circuit in order to pad the semi-autogenous grinding (“SAG”) and Ball mill liners with barren material. Once that commissioning step was completed, the grinding system was re-torqued and gold-bearing ore was introduced into the mill on April 5, 2024. Commissioning activities are currently focused on the remaining components of the processing plant – namely the gravity concentration and intensive leaching circuit, the carbon regeneration circuit, the elution circuit, cyanide destruction, and the gold room.

The tailings storage facility (“TSF”), new water treatment plant (“WTP”), tailings thickener and pipeline systems are ready for operations.

The Company anticipates the pouring of first gold at the Project on schedule during the month of April 2024.

Qualified Person

John Kiernan, P.Eng., Chief Operating Officer of the Company is the Company’s Qualified Person (QP) as defined by National Instrument 43-101 and has reviewed and approved the technical contents of this news release.

On behalf of the Board of Directors of Ascot Resources Ltd.
“Derek C. White”
President & CEO

For further information contact:

David Stewart, P.Eng.
VP, Corporate Development & Shareholder Communications
dstewart@ascotgold.com
778-725-1060 ext. 1024

ascotgold.com/news-releases/2024/...the-premier-gold-project/
Es gibt keine neuen Beiträge.


Börsen-Forum - Gesamtforum - Antwort einfügen - zum ersten Beitrag springen

Neueste Beiträge aus dem Ascot Resources Ltd Forum

Wertung Antworten Thema Verfasser letzter Verfasser letzter Beitrag
3 20 Ascot 78.77 Meters of 20.31 Grams Per Tonne Gold DasMünz Teras 20.09.24 03:51
  4 Ascot Resources peter47 peter47 13.04.24 21:08

--button_text--