Olaroz Lithium Facility
ASX/TSX ANNOUNCEMENT Quarterly Report of Operations
For The Period Ended 30 September 2015
 Production ramp up continues with production of 492 tonnes of lithium carbonate during the quarter, of which approximately 256 tonnes was produced in September, in line with forecast, 143 tonnes in August and 93 tonnes in July.
October production to date has significantly exceeded the September level. Details will be released with an Olaroz Lithium Facility Update soon after the end of the month.
All reported lithium carbonate tonnes produced are saleable tones.
All de-bottlenecking projects impacting production are now expected to be completed by
early January 2016 permitting the plant to enter the final stage of ramp up.
The process to improve utilisation of the USD deposits/Standby Letter of Credit (SBLC) instruments is in progress.
Lithium carbonate prices are now increasing to over US$6,000/tonne with further increases expected into
CY2016 and beyond as lithium market conditions continue to tighten.