First the assay lab - it is completed and the testing has been done and other than a few small issues it is ready to operate. We currently have a contractor at the site training our staff on the operation of the lab. Once the training is complete there is another step. The drilling and blasting must get about 3 weeks ahead to get the assay team time to test and determine whether each blast is waste or mill able ore. We then will take about 3 weeks to process the current stockpile of ore at the mill and then we will move into the graded ore. The whole process should be completed and the results of the assay lab (higher grade) should target beginning of next year as the reporting is a month delayed. In the past we have reported gold production quarterly but we will start reporting monthly to gain so traction in the market.
Next steps will have to come to you as part of the next corporate update as this is a requirement of the exchange. I'm sorry I can't be more specific about that.