Project Characteristics:
Location: Central Ohio
Project Size: 125 MW
Owner/Developer: EverPower:)
Project Status:
• Landowner negotiations underway
• Wind Resource data collection ongoing
• Interconnection application in progress
• Permitting studies complete
• Construction expected in 2011 www.everpower.com/ohio.html
auch ein etwas älteres Projekt, wohl mit einer Art Pilotcharakter in Ohio: "EverPower has been working since 2006 to develop and harvest this natural energy source in Ohio and on April 24, 2009 became the first ever applicant for a commercial wind farm in Ohio."
www.buckeyewindproject.com/default.htm
Statusinfo: dis.puc.state.oh.us/CaseRecord.aspx?Caseno=08-0666&link=DI
Nordex, one of the potential manufacturers that Buckeye considered
www.sconet.state.oh.us/tempx/679323.pdf
wohl am 4. Januar 2011 archiviert, dieses Dokument vom Ohio Power Siting Board...
Btw: Buckeye Wind, LLC., a subsidiary of Everpower Wind Holdings Inc (www.windaction.org/news/22752)
Und wer wird diesmal derjenige sein, der betont, dass auch Nordex diesen Auftrag von Everpower (alte bekannte) doch nicht erhält aus irgendwelchen Gründen bzw. man scheint ja auch noch Konkurrenz zu haben?
Also diese Entscheidung überlasse ich dann doch jedem einzelnen hier, vielleicht folgendes noch zur Unterstützung bei der Meinungsbildung:
-“We have been impressed with the performance and reliability of the turbines installed at the Highland Wind Farm, and from previous experience expect that Nordex's next generation of turbines will have at minimum a 97 percent availability rate,” Jim Spencer, president and CEO of EverPower Wind Holdings, said in a statement. “We are also very excited to be the first developer to install turbines manufactured at Nordex's new Arkansas plant. It reinforces what we have been saying — wind farms create American jobs.” www.bizjournals.com/memphis/news/2010/12/...wind-turbines.html
-"Nordex turbines made in the US contain more than 75% domestic content – a leading position in the industry." www.designworldonline.com/articles/7158/...ade-in-the-USA.aspx
zur Ergänzung, altes aus 2009: Buckeye Wind Project Site Layout (waren wohl auch sogar ursprünglich mal 300 MW geplant)
175 MW - Nordex N100 2.5 MW
70 WTG www.savewesternoh.org/pdf/BuckeyeShadowFlickerStudyPG23.pdf
Hmm, also von Konkurrenz war wohl damals nichts zu sehen.)
Diese PDF von J. Randall ist vom 2009.04.08...damals waren es wohl noch 175 MW, im Gegensatz zu den 125 MW heute auf www.everpower.com/ohio.html
Nur meine Meinung - keine Kaufempfehlung
"The REpower MM92 is no longer being considered."
Exergy Development Group, 2011