Der Anvil-Mining Thread

Beiträge: 7
Zugriffe: 495 / Heute: 1
newspicker:

Der Anvil-Mining Thread

 
27.01.02 19:15
Ich will Euch diese Aktie nicht länger vorenthalten, denn ich glaube,
wenn im August mit dem Abbau begonnen wird, wird sie erst richtig gen Norden
abdüsen.
Der Anvil-Mining Thread 556365cdchart.innovative-software.com/_common/...c7517fe90825816f25" style="max-width:560px" >
       


ACN 060 478 962





MEDIA RELEASE                                                                   20 December 2001


DIKULUSHI PROJECT – DRC
PROJECT DEVELOPMENT UPDATE
The recent appointment of Mr Mike O’Sullivan as Project Manager – Congo has stepped up the pace of the pre-implementation work aimed at fast tracking the Dikulushi project into production by August 2002.  Mike O’Sullivan is a seasoned mine development engineer who has considerable small mine development experience in the African environment.  

Following a site visit in early November 2001, tender documents were issued to pre-qualified engineering companies. Tenders received on 14 December 2001 are inline with previously forecast development costs and a Letter of Award is expected to be issued to the successful engineering company before the 24 December 2001.  

Pre-qualifying documents for the mining and concentrate cartage contracts are presently being received by Anvil. After evaluation, three contractors for each of the contracts will be issued with tender documents and will undertake a site visit in late January 2002.  Pre-qualification documents so far received indicate a very competitive market for the mining and concentrate transport contracts and it is expected that these contracts will be awarded in mid-March 2002.

Strengthening and re-engineering of the barge to be used to supply materials to the Dikulushi mine site during construction and to transport the Dikulushi concentrate to Zambia is forecast to be completed in mid-January 2002. The first sections of the barge will then be dispatched to Nchelenge, the Zambian port on the east side of Lake Moero in the second week of January, with the completed barge expected to undergo lake trials in early April 2002.

Based on the tenders and pre-qualifying documents received to date, the cost of the plant, barge facility and infrastructure including contingency is estimated at US$4.1 million.   Owner’s pre-production and working capital costs are estimated at US$1.7 million. The estimated total development cost for the project is therefore US$5.8 million.

The first stage of development of the Dikulushi deposit comprises of an open pit mine and Heavy Media Separation plant, which will treat ore at a rate of 250,000 tonnes per annum and produce 40,000 tonnes of concentrate per year grading approximately 40% copper and 1,230 g/t silver.   The concentrate will be shipped either to an existing smelter on the Zambian Copperbelt or a smelter in Asia where it will be toll treated to produce LME A grade copper cathode.  The forecast operating cost for copper cathode production is US 36 cents per pound, after silver credits, placing Dikulushi well within the lower quartile of the World copper production cost curve.  

Subsequent expansion, with the addition of a ball mill and flotation circuits would be funded out of project cash flows and would produce a concentrate grading 60% copper and 1,935 g/t silver, and this is expected to reduce operating costs even further.

Work is continuing on the finalisation of the documentation for the RMB Resources Ltd (“RMB Resources”) Project Financing Facility of US$4.5 million, and this is expected to be signed off by mid-January 2002. The Company is currently working through the remaining conditions precedent.

The Dikulushi deposit has a Measured, Indicated and Inferred Resource of 1.94 million tonnes at an average grade of 8.58% copper and 266 g/t silver, 85% of which is in the Measured and Indicated categories reflecting the adequacy of the drilling carried out by Anvil in the latter half of 1997.  Dikulushi is open at depth with one of the deepest drill intersections (DIK 30) intersecting 16.7 metres of 16% copper and 522 g/t silver at a vertical depth of 165 metres.

Political developments in the DRC have continued to improve during the year as evidenced by the increasing level of engagement by multilateral institutions (United Nations, World Bank and IMF) and foreign governments.  The World Bank provided a grant of US$50 million to the DRC at the end of November 2001 and the newly appointed World Bank representative moved to Kinshasa on 9 December 2001. These are significant developments particularly for the World Bank which has been absent from the DRC for a period of more than 10 years.

Executive Director Bill Turner commented, “We are very pleased with both the political developments in the DRC and the progress we have made with the pre-implementation work on the Dikulushi project. The finalization of the RMB Resources funding documentation this coming January will clear the way for Dikulushi to be in production by August 2002”.

Finally, the placement of 14 million shares at 5.5 cents, announced on 28 November 2001 has been completed with net proceeds of $769,092.  



For further information, please contact:

Bill Turner,

Executive Director

Tel: +61-89-384 4545 or +61-(0)41-1188018
Email: billt@anvil.com.au (Perth)     and    anvilminingwst@aol.com (travel)
Web site: www.anvil.com.au





Website constructed and maintained by Anvil Mining NL
Last modified December 21, 2001

Copyright © Anvil Mining, 1999



Und hier gibts  noch mehr Informationen:
www.anvil.com.au
Good Trades. N.P.
newspicker:

270% reichen Euch wohl nicht !!! Müssen es immer

 
28.01.02 21:54
1000 % sein um Euer Interesse zu wecken???
newspicker:

Latest News vom 29.01.02

 
30.01.02 16:58
       


ACN 060 478 962




MEDIA RELEASE                                                                              29 January 2002



ANVIL ISSUES “NOTICE TO PROCEED” TO MDM TO BEGIN

“PART A” DEVELOPMENT OF DIKULUSHI MINE IN DRC



Anvil Mining NL (“Anvil”) is pleased to announce that it has issued a Notice to Proceed to Metallurgical Design and Management Pty Ltd (“MDM”) of Perth, Australia for Part A of the construction contract to develop the Dikulushi mine, in the Democratic Republic of Congo (“DRC”).

Part A of the Dikulushi construction contract includes the completion of final engineering design for the Heavy Media Separation (“HMS”) plant and associated infrastructure, the transportation of the completed barge sections from Richards Bay in South Africa to the Zambian town of Nchelenge on the eastern side of Lake Moero, the establishment of a barge construction platform and docking facility at Nchelenge, the assembly of the 48 metre long and 10 metre wide self-propelled barge and its launching and commissioning, the purchase and mobilization of the necessary construction equipment and the supply of the three 500KW generator plants for the mine site.  The fixed lump sum amount for Part A of the Dikulushi construction contract is US$0.94 million. The combined value of both Parts A and B of the Dikulushi construction contract, for which MDM will take responsibility, is US$2.39 million.  

Anvil will fund its initial US$500,000 payment commitment to MDM by the transfer of 745,739 common shares in Golden Star Resources Ltd (“GSR”) to MDM.  Anvil acquired 3 million shares in GSR on 15 August 2001, at a deemed price of US40 cents per share, following a conversion of its direct interest in Bogoso Gold Limited in Ghana, to an equity interest in GSR.

Anvil intends to issue MDM a Notice to Proceed with Part B, immediately after finalisation of the US$4.5 million Project Financing Facility to be provided by RMB Resources Ltd (“RMB Resources”). Anvil is currently in an advanced stage of finalizing this funding, the documentation for which is expected to be agreed and signed in approximately three weeks.  

As part of the Dikulushi construction contract, and to satisfy the Project Financing requirements of RMB Resources, MDM has agreed to provide a Cost Overrun Facility in return for,  a) agreement with Anvil to enter into a negotiated contract for the construction of the Phase II flotation plant, and b) MDM being issued 750,000 Anvil options, exercisable at AUS12 cents and with a term of 12 months.  The willingness of MDM to provide such a facility is a reflection of the quality of the resource and the confidence MDM has in being able to develop the project on time and within budget.

The total costs for the development of Stage I of the Dikulushi project are now estimated at US$ 5.7 million, comprising the following:

Ø      Financing Costs                                                                     US$ 0.44 million

Ø      Working and Pre-production Capital                                     US$ 1.40 million

Ø      Permitting, Barge Supply and Owner’s Capital Costs            US$ 1.15 million

Ø      Process Plant, Barge Construction and Infrastructure             US$ 2.34 million

Ø      Duties and Taxes (DRC & Zambia)                                       US$ 0.14 million

Ø      Contingency                                                                          US$ 0.23 million

                    TOTAL DEVELOPMENT COST                                         US$ 5.70 million

Anvil’s Executive Director, Bill Turner commented, “The involvement of MDM and RMB Resources as partners with Anvil, brings to the Dikulushi project, significant technical and financial experience in the African environment. The flexibility shown by both MDM and RMB Resources in the lead up to initiating Part A of the Dikulushi Stage I, HMS development will ensure that the Dikulushi project moves into production in a timely manner and has the best opportunity to reach its full potential at the earliest possible time, with the planned Stage II (flotation) and Stage III (underground) expansions. Subject to finalizing the Project Financing Facility in the weeks ahead, we are on track to achieve first concentrate production in August this year.”  

Dikulushi has an independently audited Measured, Indicated and Inferred Resource (at a 2% Cu cut-off) of 1.94 million tonnes at an average grade of 8.58% copper and 266 g/t silver, 85% of which is in the Measured and Indicated categories. Since Dikulushi is open at depth, with one of the deepest drill intersections (DIK 30) intersecting 16.7 metres of 16% copper and 522 g/t silver at a vertical depth of only 165 metres, potential exists to significantly increase the resources of this deposit and extend the mine life well beyond its current 8 years.

The HMS approach is expected to produce a concentrate grading approximately 40% copper and 1,230 g/t silver.  Subsequent expansion, with the addition of a ball mill and flotation circuit (Stage II) would be funded out of project cashflows and would produce a very high-grade concentrate averaging 60% copper and 1,935 g/t silver.



For further information, please contact:

Bill Turner,

Executive Director

Tel: +61-89-384 4545 or +61-(0)41-1188018
Email: billt@anvil.com.au (Perth)     and     anvilminingwst@aol.com (travel)
Web site: www.anvil.com.au





Website constructed and maintained by Anvil Mining NL
Last modified January 30, 2002

Copyright © Anvil Mining, 1999



MfG N.P.
newspicker:

Kurse: 1.11.01 0,023 1.2.02 0,061 !!!!! o.T.

 
01.02.02 18:29
Pate100:

hey die hatte ich schonmal bei 0,025 empfohlen:-))

 
01.02.02 18:44
leider selber nicht damals gekauft:-((( Naja waren aber auch kaum Umsätze...

Gruss Pate
newspicker:

@Pate

 
01.02.02 19:16
Einsteigen ist noch nicht zu spät. Man kriegt bestimmt noch welche
so bei  0,054 .  
Bin überzeugt , sie geht noch richtig los, wenn die Produktion im August beginnt.
MfG N.P.
 
newspicker:

heute am 1.03.2002 Kursanstieg ´I` 0,085

 
01.03.02 18:45
Gestern hat sich jemand mit 260 000 Stück eingedeckt.
Es gibt keine neuen Beiträge.


Börsen-Forum - Gesamtforum - Antwort einfügen - zum ersten Beitrag springen
--button_text--