Zeitungsständer (Symbolbild).
Montag, 14.05.2018 17:55 von | Aufrufe: 248

Callinex Announces Results of Initial Preliminary Economic Assessment that Generates a 34% IRR and a $230M NPV(8)% at the Nash Creek and Superjack Projects

Zeitungsständer (Symbolbild). © AdrianHancu / iStock Editorial / Getty Images Plus / Getty Images

PR Newswire

PEA Highlights:

  • Average annual production of 77M pounds of zinc, 15M pounds of lead and 437K ounces of silver over a ten year mine life;
  • Life of Mine ("LOM") undiscounted pre-tax net cash flow of C$483M (C$293M post-tax);
  • Pre-tax IRR of a 34.1% (25.2% post-tax) and a pre-tax NPV8% of C$230M (C$128M post-tax) with a payback period of 2.4 years (2.8 years post-tax);
  • LOM all-in sustaining costs ("AISC") of C$0.37 per pound of zinc produced, net by-product credits;
  • Total pre-production capital costs of C$168 million (including 18% contingency);
  • Assumed metal prices of US$1.25 per lb of zinc, US$1.10 per lb of lead, US$17 per ounce of silver and a C$/US$ exchange rate of 0.77; and
  • Potential to materially enhance the economic return with additional drilling over the district-scale land package.

VANCOUVER, May 14, 2018 /PRNewswire/ - Callinex Mines Inc. (the "Company" or "Callinex") (TSX-V: CNX; OTCQX: CLLXF) is pleased to announce results from an independent initial Preliminary Economic Assessment ("PEA") on the Company's 100% owned Nash Creek and Superjack Projects located in the Bathurst Mining District of New Brunswick, Canada (See Figure 1 and Figure 2).

The initial PEA outlines a 10-year, 3,900 tpd open-pit mining operation with a Dense Media Separation ("DMS") plant and 1,950 tpd conventional flotation process facility at the Nash Creek Project (the "Project"). The mine plan generates a strong economic return with a pre-tax internal rate of return ("IRR") of a 34.1% (25.2% post-tax) and a pre-tax Net Present Value ("NPV") at an 8% discount rate of C$230 million (C$128 million post-tax) based on pre-production capital costs of C$168 million and a zinc price of US$1.25/lb (See Tables 1 and 2). The Company believes there is a clear opportunity to significantly enhance the project's economics with additional exploration that allows for higher grade material to be scheduled earlier in the mine plan (See Figure 3).

Max Porterfield, President and CEO, stated, "We are very pleased with the results of this initial PEA that outlines the potential for a new zinc mine at our Nash Creek Project. The results of this PEA, combined with close proximity to infrastructure and a district-scale land package, represents a highly attractive scenario for Callinex shareholders."

Cautionary Note on PEA. The PEA is preliminary in nature and it includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty that the PEA will be realized.

The Nash Creek Deposit is open for expansion in several directions with relatively few drill holes located outside of the Mineral Resource area. The 2017 drilling campaign on the Nash Creek Deposit, the first to ever be completed by the Company, led to a 74% increase in Indicated Mineral Resource zinc equivalent ("Zn Eq.") pounds and a 385% increase in Inferred Mineral Resource zinc equivalent pounds (See News Release dated April 16, 2018). Additionally, the Project encompasses several untested high-grade mineral occurrences over a highly prospective 20 km long trend. The Company plans to commence permitting while aggressively advancing exploration opportunities within this underexplored 150 km² district-scale land package.


ARIVA.DE Börsen-Geflüster

Kurse

-  
0,00%
Callinex Mines Chart

The Nash Creek and Superjack Projects benefit from world-class infrastructure within close proximity. The Nash Creek Deposit is located approximately 1 km from Provincial Highway 11 and a 230 Kv high-voltage transmission lines and only 25 km by road to Glencore's Brunswick Smelter, deep water port, railway and power plant near the town of Belledune (See Figure 1 and Figure 2).

The Superjack Project is located 90 km by highway from the Company's Nash Creek Project and 15 km southwest of the Brunswick No. 12 Mine, which was previously the largest underground mine in the world (See Figure 1).  Mineralization at the Superjack Project is hosted within a similar geological environment as the 'supergiant' Brunswick No. 12 Mine and Trevali's nearby Caribou Mine.

Callinex anticipates that development of the Nash Creek Project will provide a major economic benefit to the community of Lorne and additional nearby communities within New Brunswick. The PEA assumes that development of the project would create approximately 225 full-time jobs and contribute nearly $200 million in direct tax benefits.

The PEA was prepared under the supervision of Eugene Puritch, P. Eng., FEC, CET of P&E Mining Consultants Inc. the technical report will be filed on SEDAR within 45 days of this news release.

Opportunities and Exploration Potential

The Company's management team is very encouraged about the strong economic results generated from its initial PEA and the opportunities for further improvement with additional exploration, especially considering that only limited drilling has occurred outside of the Mineral Resource area. Notable opportunities for further improvement include:

  • Exploration or acquisition activities resulting in the addition of higher-grade material after year one of the mine plan which could have potential to significantly increase the IRR and NPV8% (See Figure 3);
  • Expand the 10-year mine life with additional exploration success at the Nash Creek Deposit, which is open for expansion, to increase the NPV8% and evaluate increasing process plant throughput with potential to lower unit costs and increase production volumes; and
  • Potential for new discoveries within a 150 km2 land package where a primary north-south corridor has several high-grade mineral occurrences up to 19% Pb+Zn at surface with very limited historic drilling.

Overview of PEA Results and Assumptions

Economic Sensitivities and Indicators

Table 1: Economic Sensitivities and Project Economics

The economic sensitivities and project economics are as follows:





Parameter

Unit

Base Case

Spot

Scenario

Zinc Price

US$/lb

$1.25

$1.40

Lead Price

US$/lb

$1.10

$1.05

Silver Price

US$/oz

$17.00

$16.70

Exchange Rate

C$/US$

0.77

0.78







Pre-tax Undiscounted Net Cash Flow

C$M

$

483.4

$

582.6

Pre-tax NPV5%

C$M

$

303.9

$

372.7

Pre-tax NPV8%

C$M

$

230.2

$

286.6

Pre-tax IRR

%

34.1%

39.2%

Pre-tax Payback Period

years

2.4

2.1







After-tax Undiscounted Net Cash Flow

C$M

$

292.5

$

350.7

After-tax NPV5%

C$M

$

175.7

$

216.2

After-tax NPV8%

C$M

$

127.6

$

160.7

After-tax IRR

%

25.2%

28.8%

After-tax Payback Period

years

2.8

2.6







Net Smelter Return

C$/t DMS

plant feed

$

80.13

$

87.07

Operating Margin

Werbung

Mehr Nachrichten zur Callinex Mines Aktie kostenlos abonnieren

E-Mail-Adresse
Benachrichtigungen von ARIVA.DE
(Mit der Bestellung akzeptierst du die Datenschutzhinweise)

Hinweis: ARIVA.DE veröffentlicht in dieser Rubrik Analysen, Kolumnen und Nachrichten aus verschiedenen Quellen. Die ARIVA.DE AG ist nicht verantwortlich für Inhalte, die erkennbar von Dritten in den „News“-Bereich dieser Webseite eingestellt worden sind, und macht sich diese nicht zu Eigen. Diese Inhalte sind insbesondere durch eine entsprechende „von“-Kennzeichnung unterhalb der Artikelüberschrift und/oder durch den Link „Um den vollständigen Artikel zu lesen, klicken Sie bitte hier.“ erkennbar; verantwortlich für diese Inhalte ist allein der genannte Dritte.


Andere Nutzer interessierten sich auch für folgende News